  • Mundra TPP (4620 MW)- World’s largest single location private coal based power project.
  • Mundra Phase-III - 2 x 660 MW: First coal based supercritical thermal project in the world, registered for CDM with UNFCCC.
  • Tiroda Phase-I - 2 x 660 MW: Second coal based supercritical thermal project in the world registered for CDM with UNFCCC.
  • First in the world, who has developed methodology and got it approved for High Voltage Direct Current power transmission for CDM with UNFCCC.
  • Commissioned largest Amorphous Silicon thin film solar power project in the world in less than 5.5 months.
  •  Longest and largest HVDC transmission system installed by any private player in the worldin a time span of less than 24 months.
  • Mundra 4620MW power plant consists of 9 units has been installed in less than 300Hac land: Lowest Area/ MW coal based power plant in the country.
  • Unit 5 of Mundra TPP (660MW): First Supercritical unit to be synchronized in India. The unit was synchronized with in 36 months from inception.
  • Commissioned four super critical thermal power generating units at single location in one financial year (2011-12) i.e. Unit-6, Unit-7, Unit-8 & Unit-9 of Mundra TPP (2640 MW).
  •  Mundra super critical units 6 & 9 achieved synchronization from boiler light up in less than 3.5 months.
  • 2 super critical units (Unit-8 and Unit-9 of Mundra TPP) completed the steam blowing within 2 days from boiler light up.
  • Mundra unit 3, 5 & 9: 3 units in a single location achieved full load operation from synchronization in less than 4 days.